Beach Nourishment & Preservation

2025 / 2026 Beach Nourishment Project

2025 Beach Nourishment Banner

PROGRESS TRACKER

FEBRUARY 2, 2026

As of NOON on Saturday, January 31, sand placement operations have been COMPLETED for the Off-Shore Oak Island (OS-OKI) portion of the Project. To allow for the demobilization and removal of equipment, the area of W Beach Drive from 69th Pl West to The Point is now being CLOSED daily to all thru-traffic from 7:00 AM - 4:00 PM until February 13.

Beach Nourishment Traffic Notice

Sand placement for the Wilmington Harbor portion of the Project being conducted by the US Army Corps of Engineers (USACE) is still active, and is currently near the area of SE 69th Street; expecting to be completed by Saturday, February 7.

As sand placement operations are completed, it is more important to ensure safety in the demobilization and removal of equipment. Please follow all detours, road closures, and onsite traffic direction as these projects work to remove the many pieces of large equipment and heavy machinery used in the Project

  • COMPLETED: Crews have completed sand placement operations in the areas of 
    • SE 52nd St to 5th Pl W (OS-OKI)
    • 13th Pl W to 33rd Pl W (OS-OKI)
    • 48th Pl W to The Point (OS-OKI)
    • McGlamery St to SE 70th St (USACE)
  • CURRENT: Crews with USACE are still working in the area of: 
    • SE 69th St. to SE 63rd St. 
  • FUTURE: Crews with the OS-OKI project are working to demobilize equipment in the area from 69th Pl W to The Point. The USACE expects to be completed with sand placement, and being demobilizing equipment by Saturday, February 7.

PROGRESS MAP

The Progress Tracker Map provided below shows operations areas which are:

  • COMPLETEDCURRENT • FUTURE

PROJECT NOTICES

  • MULTIPLE ZONES NOTICE  As of January 5, 2026 the Project is now active in multiple work zones, as sand placement for the Wilmington Harbor (USACE) and the Oak Island Off-Shore (OS-OKI) projects are both in operation on the public beach areas.
  • DREDGING NOTICE As of Friday, November 21 at 4:30 PM -- Dredging & Sand Placement Operations are NOW ACTIVE.
  • OPERATIONS NOTICE Work for this project will be conducted 24 hours per day, resulting in effects which include noisemoving machinery, ground vibrations, and closed beach areas. To ensure the safety of everyone, please be sure to respect the boundaries of any closed staging or construction areas, and do not distract crews onsite by attempting to speak with them or ask questions.
  • CLOSURE NOTICE The parking lot for the Kevin Bell Skatepark and the adjacent Beach Access Location on SE 49th Street, will be CLOSED to allow for project staging.
  • SURVEY NOTICE A surveyor from Weeks Marine (the dredging contractor) will be performing Before Dredging (BD) After Dredging (AD) Surveys on the beach regularly throughout the project.
About The 2025 / 2026 Project
Project Update History
Project FAQ

 


BEACH MANAGEMENT

Click the tabs below for more information on the Town's Beach Management Plans, as well as previously completed Beach Nourishment Projects.

Beach Management Plans
Previous Nourishment Projects
General Information